# DurationType of IfcTaskType should affect FreeFloat and TotalFloat

**URL:** <https://forums.buildingsmart.org/t/durationtype-of-ifctasktype-should-affect-freefloat-and-totalfloat/3697>\
**Category:** Developers\
**Tags:** ifc4-errata\
**Created:** [June 1, 2021, 10:51pm UTC](https://forums.buildingsmart.org/t/durationtype-of-ifctasktype-should-affect-freefloat-and-totalfloat/3697 "2021-06-01T22:51:06Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![Moult](https://sea2.discourse-cdn.com/flex016/user_avatar/forums.buildingsmart.org/moult/32/196_2.png) [@Moult](https://forums.buildingsmart.org/u/Moult)\
**Post date:** [June 1, 2021, 10:51pm UTC](https://forums.buildingsmart.org/t/durationtype-of-ifctasktype-should-affect-freefloat-and-totalfloat/3697/1 "2021-06-01T22:51:06Z")

</div>

The duration type description currently states:

> Enables to specify the type of duration values for _ScheduleDuration_ , _ActualDuration_ and _RemainingTime_ . The duration type is either work time or elapsed time.

What is not mentioned in this list is the durations for `FreeFloat` and `TotalFloat`. I believe these durations should also be considered for `DurationType`.

I propose changing the docs to say:

> Enables to specify the type of duration values for _ScheduleDuration_ , _ActualDuration_, _RemainingTime_, _FreeFloat_, and _TotalFloat_. The duration type is either work time or elapsed time.

---

<div class="post-metadata">

**Author:** ![Moult](https://sea2.discourse-cdn.com/flex016/user_avatar/forums.buildingsmart.org/moult/32/196_2.png) [@Moult](https://forums.buildingsmart.org/u/Moult)\
**Post date:** [June 4, 2021, 2:25am UTC](https://forums.buildingsmart.org/t/durationtype-of-ifctasktype-should-affect-freefloat-and-totalfloat/3697/2 "2021-06-04T02:25:02Z")

</div>

Just to clarify, the docs state this for `FreeFloat` and `TotalFloat`:

> It is a calculated elapsed time value.

I believe this is incorrect. I believe that the float may also be affected by duration type, and by either be represented by elapsed time or by work time. This matches the behaviour in existing scheduling software like P6, which can show floats in `WORKTIME` as well.