# Definitions of FreeFloat and TotalFloat in IfcTaskTime seem incorrect

**URL:** <https://forums.buildingsmart.org/t/definitions-of-freefloat-and-totalfloat-in-ifctasktime-seem-incorrect/3696>\
**Category:** Developers\
**Tags:** ifc4-errata\
**Created:** [June 1, 2021, 10:46pm UTC](https://forums.buildingsmart.org/t/definitions-of-freefloat-and-totalfloat-in-ifctasktime-seem-incorrect/3696 "2021-06-01T22:46:31Z")\
**Posts on this page:** 1\
**Page:** 1

<div class="post-metadata">

**Author:** ![Moult](https://sea2.discourse-cdn.com/flex016/user_avatar/forums.buildingsmart.org/moult/32/196_2.png) [@Moult](https://forums.buildingsmart.org/u/Moult)\
**Post date:** [June 1, 2021, 10:46pm UTC](https://forums.buildingsmart.org/t/definitions-of-freefloat-and-totalfloat-in-ifctasktime-seem-incorrect/3696/1 "2021-06-01T22:46:31Z")

</div>

The current definitions in the docs are:

> **FreeFloat** : The amount of time during which the start or finish of a task may be varied without any effect on the overall programme of work. It is a calculated elapsed time value.
> 
> **TotalFloat** : The difference between the duration available to carry out a task and the scheduled duration of the task. It is a calculated elapsed time value.

The definitions seem to be swapped. The proper definition should be:

> **TotalFloat** : the amount of time that a task can be delayed without causing a delay to the project completion date.
> 
> **FreeFloat** : the amount of time that a task can be delayed without causing a delay to subsequent tasks.